McLeod Area Roads Project
We are making improvements to the streets and infrastructure in the McLeod Drive area (McLeod Drive, Gilibank Drive, Lacey Court and Marksbury Court).
The proposed work will include:
- Full depth road reconstruction on McLeod Drive and portion of Lacey Court;
- Full asphalt and curb replacement on Gilbank Drive and portion of Lacey Court;
- Asphalt mill and overlay on Marksbury Court, with concrete curb spot repairs
- Watermain lining on McLeod Drive and Lacey Court
- Storm sewer lining and new guiderail on Marksbury Court
- Sewer and sidewalk spot repairs and minor road drainage improvements
- Brightening of existing streetlights with potential addition ofContinue reading
We are making improvements to the streets and infrastructure in the McLeod Drive area (McLeod Drive, Gilibank Drive, Lacey Court and Marksbury Court).
The proposed work will include:
- Full depth road reconstruction on McLeod Drive and portion of Lacey Court;
- Full asphalt and curb replacement on Gilbank Drive and portion of Lacey Court;
- Asphalt mill and overlay on Marksbury Court, with concrete curb spot repairs
- Watermain lining on McLeod Drive and Lacey Court
- Storm sewer lining and new guiderail on Marksbury Court
- Sewer and sidewalk spot repairs and minor road drainage improvements
- Brightening of existing streetlights with potential addition of a streetlight pole on Marksbury Court
What to expect during construction:
- Signage will be posted in the area and construction notices will be distributed.
- Regular construction hours from 7am to 8 pm, Monday to Friday. Contractor may work Saturday as needed.
- Sidewalks will be closed where needed for repairs.
- Access to McLeod Dr, Gilbank Dr, Marksbury Ct and Lacey Ct will be for local traffic only during construction. Please be aware of construction activity and personnel.
-
Project Update - October 23rd
Share Project Update - October 23rd on Facebook Share Project Update - October 23rd on Twitter Share Project Update - October 23rd on Linkedin Email Project Update - October 23rd linkThe same project works will continue as yesterday. See below:
Gilbank Drive: All restoration works are complete including sod. Please contact Jeremy if there are any concerns or missed items. Final asphalt will be placed in the next 2 weeks.
McLeod Drive: Sidewalk removal and replacement are underway. Boulevard and driveway restorations are ongoing.
*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*
Lacey Court: Sidewalk removal and replacement are underway. Boulevard and driveway restorations are ongoing.
Marksbury Court: All restoration works are complete including sod. Please contact Jeremy if there are any concerns or missed items.
*PLEASE NOTE: Interlock/edger restorations are ongoing. Any missing sections will needed to be sourced and completed. Upon completion, it will be noted here and complaints should made at that time. Sprinkler repairs are being scheduled and will work with home owners directly when on site*
-
Project Update - October 22nd
Share Project Update - October 22nd on Facebook Share Project Update - October 22nd on Twitter Share Project Update - October 22nd on Linkedin Email Project Update - October 22nd linkGilbank Drive: All restoration works are complete including sod. Please contact Jeremy if there are any concerns or missed items. Final asphalt will be placed in the next 2 weeks.
McLeod Drive: Sidewalk removal and replacement are underway. Boulevard and driveway restorations are ongoing.
*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*
Lacey Court: Sidewalk removal and replacement are underway. Boulevard and driveway restorations are ongoing.
Marksbury Court: All restoration works are complete including sod. Please contact Jeremy if there are any concerns or missed items.
*PLEASE NOTE: Interlock/edger restorations are ongoing. Any missing sections will needed to be sourced and completed. Upon completion, it will be noted here and complaints should made at that time. Sprinkler repairs are being scheduled and will work with home owners directly when on site*
-
Project Update - October 20th
Share Project Update - October 20th on Facebook Share Project Update - October 20th on Twitter Share Project Update - October 20th on Linkedin Email Project Update - October 20th linkThe same project works will continue as Friday. See below:
Gilbank Drive: Driveway and boulevard restoration works are ongoing. Sod will be done on all streets at the same time.
McLeod Drive: Paving is complete. Sidewalk removal and replacement to commence after paving is complete. Boulevard and driveway restorations to follow paving as well.
*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*
Lacey Court: Paving is complete. Sidewalk removal and replacement to commence after paving is complete. Boulevard and driveway restorations to follow paving as well.
Marksbury Court: Boulevard restoration is complete. Sod will be done on all streets at the same time.
PLEASE NOTE: Interlock/edger restorations are ongoing. Any missing sections will needed to be sourced and completed. Upon completion, it will be noted here and complaints should made at that time.
-
Project Update - October 17th
Share Project Update - October 17th on Facebook Share Project Update - October 17th on Twitter Share Project Update - October 17th on Linkedin Email Project Update - October 17th linkGilbank Drive: Driveway and boulevard restoration works are ongoing. Sod will be done on all streets at the same time.
McLeod Drive: Paving is complete. Sidewalk removal and replacement to commence after paving is complete. Boulevard and driveway restorations to follow paving as well.
*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*
Lacey Court: Paving is complete. Sidewalk removal and replacement to commence after paving is complete. Boulevard and driveway restorations to follow paving as well.
Marksbury Court: Boulevard restoration is complete. Sod will be done on all streets at the same time.
PLEASE NOTE: Interlock/edger restorations are ongoing. Any missing sections will needed to be sourced and completed. Upon completion, it will be noted here and complaints should made at that time.
-
Project Update - October 15th
Share Project Update - October 15th on Facebook Share Project Update - October 15th on Twitter Share Project Update - October 15th on Linkedin Email Project Update - October 15th linkThe same project works will continue as yesterday. See below:
Gilbank Drive: Driveway and boulevard restoration work is ongoing. Sod placement will be completed on all streets at the same time.McLeod Drive: Paving is scheduled for October 16th. Sidewalk removal and replacement will begin once paving is complete, followed by boulevard and driveway restorations.
*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*
Lacey Court: Paving is scheduled for October 16th. Sidewalk removal and replacement will commence after paving, with boulevard and driveway restorations to follow.
Marksbury Court: Boulevard restoration is complete. Sod placement will occur concurrently across all streets.
-
Project Update - October 14th
Share Project Update - October 14th on Facebook Share Project Update - October 14th on Twitter Share Project Update - October 14th on Linkedin Email Project Update - October 14th linkGilbank Drive: Driveway and boulevard restoration work is ongoing. Sod placement will be completed on all streets at the same time.
McLeod Drive: Paving is scheduled for October 16th. Sidewalk removal and replacement will begin once paving is complete, followed by boulevard and driveway restorations.
*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*
Lacey Court: Paving is scheduled for October 16th. Sidewalk removal and replacement will commence after paving, with boulevard and driveway restorations to follow.
Marksbury Court: Boulevard restoration is complete. Sod placement will occur concurrently across all streets.
-
Important Notice - Pool Water Discharge
Share Important Notice - Pool Water Discharge on Facebook Share Important Notice - Pool Water Discharge on Twitter Share Important Notice - Pool Water Discharge on Linkedin Email Important Notice - Pool Water Discharge linkGood morning,
Residents are reminded to not discharge pool water directly onto the road. This practice is prohibited under the Town's bylaws and can negatively impact ongoing construction work on McLeod Drive.
Improper discharge may cause flooding, erosion, or damage to newly constructed infrastructure. Residents are asked to follow proper pool drainage procedures in accordance with Town regulations.
Thank you.
-
Project Update - October 9th & 10th
Share Project Update - October 9th & 10th on Facebook Share Project Update - October 9th & 10th on Twitter Share Project Update - October 9th & 10th on Linkedin Email Project Update - October 9th & 10th linkSimilar construction works will continue for the remaining of the week, see below:
Gilbank Drive: Driveway and boulevard restoration works are ongoing.
McLeod Drive: Sidewalk removal and replacement to begin next week. Paving has been scheduled for mid next week.
*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*
Lacey Court: Paving has been scheduled for mid next week. Sidewalk removal and replacements to begin next week.
Marksbury Court: Boulevard restoration is ongoing.
-
Project Update - October 7th
Share Project Update - October 7th on Facebook Share Project Update - October 7th on Twitter Share Project Update - October 7th on Linkedin Email Project Update - October 7th linkGood morning,
Works today will proceed the same as yesterday, see below:
Gilbank Drive: Driveway and boulevard restoration works are ongoing.
McLeod Drive: Curb has been poured and driveway access restored. Sidewalk removal and replacement to begin this week. Placing of additional stone on road will also be occurring this week.
*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*
Lacey Court: Curb has been poured. Road grading to begin this week. Sidewalk removal and replacements will also begin this week.
Marksbury Court: Guard rail installation is complete, with clean-up to follow. Driveway restorations are ongoing. Street light has been installed.
-
Project Update - October 6th
Share Project Update - October 6th on Facebook Share Project Update - October 6th on Twitter Share Project Update - October 6th on Linkedin Email Project Update - October 6th linkGilbank Drive: Driveway and boulevard restoration works are ongoing.
McLeod Drive: Curb has been poured and driveway access restored. Sidewalk removal and replacement to begin this week. Placing of additional stone on road will also be occurring this week.
*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*
Lacey Court: Curb has been poured. Road grading to begin this week. Sidewalk removal and replacements will also begin this week.
Marksbury Court: Guard rail installation is complete, with clean-up to follow. Driveway restorations are ongoing. Street light has been installed.
Signup Banner
Who's Listening
-
JC
Email jcarnovale@aurora.ca
Key Dates
-
October 22 2024
Lifecycle
-
Phase 1- Design
McLeod Area Roads Project has finished this stageConceptual Design
-
Phase 2- Finalize Design & Issue for Tender
McLeod Area Roads Project has finished this stageWinter 2024
-
Phase 3- Construction
McLeod Area Roads Project is currently at this stageSpring 2025
-
Phase 4- Anticipated Completion
this is an upcoming stage for McLeod Area Roads ProjectNovember 2025