Project Update - October 14th
Gilbank Drive: Driveway and boulevard restoration work is ongoing. Sod placement will be completed on all streets at the same time.
McLeod Drive: Paving is scheduled for October 16th. Sidewalk removal and replacement will begin once paving is complete, followed by boulevard and driveway restorations.
*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*
Lacey Court: Paving is scheduled for October 16th. Sidewalk removal and replacement will commence after paving, with boulevard and driveway restorations to follow.
Marksbury Court: Boulevard restoration is complete. Sod placement will occur concurrently across all streets.