Project Update - October 14th

Gilbank Drive: Driveway and boulevard restoration work is ongoing. Sod placement will be completed on all streets at the same time.

McLeod Drive: Paving is scheduled for October 16th. Sidewalk removal and replacement will begin once paving is complete, followed by boulevard and driveway restorations.

*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*

Lacey Court: Paving is scheduled for October 16th. Sidewalk removal and replacement will commence after paving, with boulevard and driveway restorations to follow.

Marksbury Court: Boulevard restoration is complete. Sod placement will occur concurrently across all streets.

Share Project Update - October 14th on Facebook Share Project Update - October 14th on Twitter Share Project Update - October 14th on Linkedin Email Project Update - October 14th link
#<Object:0x00007f6eb0a4cba0>