Project Update - October 9th & 10th

Similar construction works will continue for the remaining of the week, see below:

Gilbank Drive: Driveway and boulevard restoration works are ongoing.

McLeod Drive: Sidewalk removal and replacement to begin next week. Paving has been scheduled for mid next week.

*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*

Lacey Court: Paving has been scheduled for mid next week. Sidewalk removal and replacements to begin next week.

Marksbury Court: Boulevard restoration is ongoing.


Share Project Update - October 9th & 10th on Facebook Share Project Update - October 9th & 10th on Twitter Share Project Update - October 9th & 10th on Linkedin Email Project Update - October 9th & 10th link
#<Object:0x000000002f691750>