Project Update - October 6th

Gilbank Drive: Driveway and boulevard restoration works are ongoing.

McLeod Drive: Curb has been poured and driveway access restored. Sidewalk removal and replacement to begin this week. Placing of additional stone on road will also be occurring this week.

*PLEASE NOTE: VEHICLE ACCESS TO HOMES WILL BE IMPACTED DURING SIDEWALK REMOVAL AND REPLACMENT. THERE WILL BE A MINIMUM 24-HOUR PERIOD WITH NO VEHICLE ACCESS*

Lacey Court: Curb has been poured. Road grading to begin this week. Sidewalk removal and replacements will also begin this week.

Marksbury Court: Guard rail installation is complete, with clean-up to follow. Driveway restorations are ongoing. Street light has been installed.