We are building a multi-use path (MUP) along Yonge Street that will run from Bloomington Road north to the GO Train Bridge. This north-south path will be designed to allow for a wide-range of recreational uses such as cycling, walking, jogging and wheelchair access. The goal for the Yonge Street MUP is to allow the community to connect to key destinations in Town such as the Aurora GO Station, existing trails, schools and local businesses. Checkout the flyover view below to see the proposed trajectory of the future MUP.

Currently, active transportation facilities are not provided along this stretch of Yonge Street. Cyclists share the road with motorists without dedicated and separated facilities, and pedestrians are using the shoulder of the road to access services and amenities north of this area. This multi-use path will increase safety for all road users.


We are building a multi-use path (MUP) along Yonge Street that will run from Bloomington Road north to the GO Train Bridge. This north-south path will be designed to allow for a wide-range of recreational uses such as cycling, walking, jogging and wheelchair access. The goal for the Yonge Street MUP is to allow the community to connect to key destinations in Town such as the Aurora GO Station, existing trails, schools and local businesses. Checkout the flyover view below to see the proposed trajectory of the future MUP.

Currently, active transportation facilities are not provided along this stretch of Yonge Street. Cyclists share the road with motorists without dedicated and separated facilities, and pedestrians are using the shoulder of the road to access services and amenities north of this area. This multi-use path will increase safety for all road users.


  • Week of July 27 - July 31, 2026

    Share Week of July 27 - July 31, 2026 on Facebook Share Week of July 27 - July 31, 2026 on X (formerly Twitter) Share Week of July 27 - July 31, 2026 on Linkedin Email Week of July 27 - July 31, 2026 link

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

  • July 24, 2026

    Share July 24, 2026 on Facebook Share July 24, 2026 on X (formerly Twitter) Share July 24, 2026 on Linkedin Email July 24, 2026 link

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

  • July 23, 2026

    Share July 23, 2026 on Facebook Share July 23, 2026 on X (formerly Twitter) Share July 23, 2026 on Linkedin Email July 23, 2026 link

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

  • July 22, 2026

    Share July 22, 2026 on Facebook Share July 22, 2026 on X (formerly Twitter) Share July 22, 2026 on Linkedin Email July 22, 2026 link

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

  • July 21, 2026

    Share July 21, 2026 on Facebook Share July 21, 2026 on X (formerly Twitter) Share July 21, 2026 on Linkedin Email July 21, 2026 link

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

  • July 20, 2026

    Share July 20, 2026 on Facebook Share July 20, 2026 on X (formerly Twitter) Share July 20, 2026 on Linkedin Email July 20, 2026 link

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

  • July 17, 2026

    Share July 17, 2026 on Facebook Share July 17, 2026 on X (formerly Twitter) Share July 17, 2026 on Linkedin Email July 17, 2026 link

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

  • July 16, 2026

    Share July 16, 2026 on Facebook Share July 16, 2026 on X (formerly Twitter) Share July 16, 2026 on Linkedin Email July 16, 2026 link

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

  • July 15, 2026

    Share July 15, 2026 on Facebook Share July 15, 2026 on X (formerly Twitter) Share July 15, 2026 on Linkedin Email July 15, 2026 link

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

  • July 14, 2026

    Share July 14, 2026 on Facebook Share July 14, 2026 on X (formerly Twitter) Share July 14, 2026 on Linkedin Email July 14, 2026 link

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.

    Tree removals and rough grading for the multi-use path will continue throughout the week.

    Daily lane closures will occur along Yonge St between Bloomington Road and Industrial Parkway. Drivers should expect delays and use caution when travelling through the area.