Yonge Street Multi-Use Path

Share Yonge Street Multi-Use Path on Facebook Share Yonge Street Multi-Use Path on X (formerly Twitter) Share Yonge Street Multi-Use Path on Linkedin Email Yonge Street Multi-Use Path link

We are building a multi-use path (MUP) along Yonge Street that will run from Bloomington Road north to the GO Train Bridge. This north-south path will be designed to allow for a wide-range of recreational uses such as cycling, walking, jogging and wheelchair access. The goal for the Yonge Street MUP is to allow the community to connect to key destinations in Town such as the Aurora GO Station, existing trails, schools and local businesses. Checkout the flyover view below to see the proposed trajectory of the future MUP.

Currently, active transportation facilities are not provided along this stretch of Yonge Street. Cyclists share the road with motorists without dedicated and separated facilities, and pedestrians are using the shoulder of the road to access services and amenities north of this area. This multi-use path will increase safety for all road users.


We are building a multi-use path (MUP) along Yonge Street that will run from Bloomington Road north to the GO Train Bridge. This north-south path will be designed to allow for a wide-range of recreational uses such as cycling, walking, jogging and wheelchair access. The goal for the Yonge Street MUP is to allow the community to connect to key destinations in Town such as the Aurora GO Station, existing trails, schools and local businesses. Checkout the flyover view below to see the proposed trajectory of the future MUP.

Currently, active transportation facilities are not provided along this stretch of Yonge Street. Cyclists share the road with motorists without dedicated and separated facilities, and pedestrians are using the shoulder of the road to access services and amenities north of this area. This multi-use path will increase safety for all road users.


  • Week of November 16 - 20, 2026

    Share Week of November 16 - 20, 2026 on Facebook Share Week of November 16 - 20, 2026 on X (formerly Twitter) Share Week of November 16 - 20, 2026 on Linkedin Email Week of November 16 - 20, 2026 link

    Construction of the retaining wall has now been complete.

    Paving of the multi-use path as well as various concrete work will continue throughout the week.

    Please note, while the multi-use path looks complete it is still closed for construction, construction activities on the site are still on-going as it is an active construction site so please continue to proceed with caution while in the area.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

    Construction of the retaining wall has now been complete.

    Paving of the multi-use path as well as various concrete work will continue throughout the week.

    Please note, while the multi-use path looks complete it is still closed for construction, construction activities on the site are still on-going as it is an active construction site so please continue to proceed with caution while in the area.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

  • Week of November 9 - 13, 2026

    Share Week of November 9 - 13, 2026 on Facebook Share Week of November 9 - 13, 2026 on X (formerly Twitter) Share Week of November 9 - 13, 2026 on Linkedin Email Week of November 9 - 13, 2026 link

    Happy Monday all,

    Construction of the retaining wall will continue throughout the week.

    Paving of the multi-use path will continue this week with concrete work to begin this week in various locations.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

    Happy Monday all,

    Construction of the retaining wall will continue throughout the week.

    Paving of the multi-use path will continue this week with concrete work to begin this week in various locations.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

  • Week of November 2 - 6, 2026

    Share Week of November 2 - 6, 2026 on Facebook Share Week of November 2 - 6, 2026 on X (formerly Twitter) Share Week of November 2 - 6, 2026 on Linkedin Email Week of November 2 - 6, 2026 link

    Grading for the multi-use path, storm sewer work, and retaining wall construction will continue throughout the week.

    Paving of the multi-use path will begin this week starting on the south-west end.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

    Grading for the multi-use path, storm sewer work, and retaining wall construction will continue throughout the week.

    Paving of the multi-use path will begin this week starting on the south-west end.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

  • Week of October 26 - 30, 2026

    Share Week of October 26 - 30, 2026 on Facebook Share Week of October 26 - 30, 2026 on X (formerly Twitter) Share Week of October 26 - 30, 2026 on Linkedin Email Week of October 26 - 30, 2026 link

    Grading for the multi-use path, storm sewer work, and retaining wall construction will continue throughout the week. Ridge Road is re-opened at Yonge Street.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

    Grading for the multi-use path, storm sewer work, and retaining wall construction will continue throughout the week. Ridge Road is re-opened at Yonge Street.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

  • Ridge Road Temporary Closure Update

    Share Ridge Road Temporary Closure Update on Facebook Share Ridge Road Temporary Closure Update on X (formerly Twitter) Share Ridge Road Temporary Closure Update on Linkedin Email Ridge Road Temporary Closure Update link

    As the project progresses, Ridge Road will be re-opened and access to and from Yonge Street is expected to be re-instated end of day today.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your support and patience, have a wonderful weekend.

    As the project progresses, Ridge Road will be re-opened and access to and from Yonge Street is expected to be re-instated end of day today.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your support and patience, have a wonderful weekend.

  • Week of October 19 - 23, 2026

    Share Week of October 19 - 23, 2026 on Facebook Share Week of October 19 - 23, 2026 on X (formerly Twitter) Share Week of October 19 - 23, 2026 on Linkedin Email Week of October 19 - 23, 2026 link

    Grading for the multi-use path, storm sewer work, and retaining wall construction will continue throughout the week.

    Ridge Road remains closed at Yonge Street and is expected to remain closed throughout October. Please use Glensteeple Trail to access Yonge Street. The temporary bus stop at Glensteeple trail remains operational for riders to use.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

    Grading for the multi-use path, storm sewer work, and retaining wall construction will continue throughout the week.

    Ridge Road remains closed at Yonge Street and is expected to remain closed throughout October. Please use Glensteeple Trail to access Yonge Street. The temporary bus stop at Glensteeple trail remains operational for riders to use.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

  • Week of October 12 - 16, 2026

    Share Week of October 12 - 16, 2026 on Facebook Share Week of October 12 - 16, 2026 on X (formerly Twitter) Share Week of October 12 - 16, 2026 on Linkedin Email Week of October 12 - 16, 2026 link

    Happy Thanksgiving to all and hope everyone had a wonderful long weekend.

    Grading for the multi-use path, storm sewer work, and retaining wall construction will continue throughout the week.

    Ridge Road remains closed at Yonge Street and is expected to remain closed throughout October. Please use Glensteeple Trail to access Yonge Street. The temporary bus stop at Glensteeple trail remains operational for riders to use.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

    Happy Thanksgiving to all and hope everyone had a wonderful long weekend.

    Grading for the multi-use path, storm sewer work, and retaining wall construction will continue throughout the week.

    Ridge Road remains closed at Yonge Street and is expected to remain closed throughout October. Please use Glensteeple Trail to access Yonge Street. The temporary bus stop at Glensteeple trail remains operational for riders to use.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

  • Week of October 5 - 9, 2026

    Share Week of October 5 - 9, 2026 on Facebook Share Week of October 5 - 9, 2026 on X (formerly Twitter) Share Week of October 5 - 9, 2026 on Linkedin Email Week of October 5 - 9, 2026 link

    Grading for the multi-use path, storm sewer work, and retaining wall construction will continue throughout the week.

    Ridge Road remains closed at Yonge Street and is expected to remain closed throughout October. Please use Glensteeple Trail to access Yonge Street.

    The temporary bus stop at Glensteeple Trail is now operational for riders to use.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

    Grading for the multi-use path, storm sewer work, and retaining wall construction will continue throughout the week.

    Ridge Road remains closed at Yonge Street and is expected to remain closed throughout October. Please use Glensteeple Trail to access Yonge Street.

    The temporary bus stop at Glensteeple Trail is now operational for riders to use.

    Daily lane closures are expected on Yonge Street between Bloomington Road and Industrial Parkway. Please allow extra travel time and use caution when passing through the work area.

    Thank you for your patience as construction progresses.

  • Temporary Bus Stop & Ridge Road Closure

    Share Temporary Bus Stop & Ridge Road Closure on Facebook Share Temporary Bus Stop & Ridge Road Closure on X (formerly Twitter) Share Temporary Bus Stop & Ridge Road Closure on Linkedin Email Temporary Bus Stop & Ridge Road Closure link

    Residents are reminded that Ridge Rad will be closed at Yonge Street starting Monday, October 5. Please use Glensteeple trail for access to and from Yonge Street during the closure.

    The existing bus stop near ridge road will remain open. An additional temporary bus stop will be installed at the corner of Yonge Street and Glensteeple Trail on Tuesday, October 6 as well during this closure.


    Residents are reminded that Ridge Rad will be closed at Yonge Street starting Monday, October 5. Please use Glensteeple trail for access to and from Yonge Street during the closure.

    The existing bus stop near ridge road will remain open. An additional temporary bus stop will be installed at the corner of Yonge Street and Glensteeple Trail on Tuesday, October 6 as well during this closure.


  • Recycling & Garbage Collection During Ridge Road Closure

    Share Recycling & Garbage Collection During Ridge Road Closure on Facebook Share Recycling & Garbage Collection During Ridge Road Closure on X (formerly Twitter) Share Recycling & Garbage Collection During Ridge Road Closure on Linkedin Email Recycling & Garbage Collection During Ridge Road Closure link
    supporting image

    Residents are reminded that Ridge Road will be closed at Yonge Street starting Monday, October 5. Please use Glensteeple Trail to access Yonge Street during the closure.

    Garbage collection will continue for properties affected by the closure. Staff will work with the contractor on site to ensure garbage is picked up.

    Thank you for your patience and cooperation as work continues on the Yonge Street Multi-Use Path project.

    Residents are reminded that Ridge Road will be closed at Yonge Street starting Monday, October 5. Please use Glensteeple Trail to access Yonge Street during the closure.

    Garbage collection will continue for properties affected by the closure. Staff will work with the contractor on site to ensure garbage is picked up.

    Thank you for your patience and cooperation as work continues on the Yonge Street Multi-Use Path project.