Share Aurora Town Hall/Seniors’ Centre Parking Lot Rehabilitation and Reflection Space Construction on Facebook Share Aurora Town Hall/Seniors’ Centre Parking Lot Rehabilitation and Reflection Space Construction on X (formerly Twitter) Share Aurora Town Hall/Seniors’ Centre Parking Lot Rehabilitation and Reflection Space Construction on Linkedin Email Aurora Town Hall/Seniors’ Centre Parking Lot Rehabilitation and Reflection Space Construction link

We’re giving the Town Hall and Seniors’ Centre parking lots a refresh!

This project will make it easier and safer for everyone to park, walk, and get around. We’re replacing the pavement, improving walkways and entrances, and adding brighter, energy‑efficient lighting. The south parking lot will also be reconfigured to create 13 new parking spaces.

Before parking lot work begins, roof repairs at Town Hall and the Seniors’ Centre will be completed. And out front of Town Hall, we’re creating a new community reflection space—a welcoming place for residents to gather, pause, and connect.

We’re giving the Town Hall and Seniors’ Centre parking lots a refresh!

This project will make it easier and safer for everyone to park, walk, and get around. We’re replacing the pavement, improving walkways and entrances, and adding brighter, energy‑efficient lighting. The south parking lot will also be reconfigured to create 13 new parking spaces.

Before parking lot work begins, roof repairs at Town Hall and the Seniors’ Centre will be completed. And out front of Town Hall, we’re creating a new community reflection space—a welcoming place for residents to gather, pause, and connect.

  • July 14th, 2026

    Share July 14th, 2026 on Facebook Share July 14th, 2026 on X (formerly Twitter) Share July 14th, 2026 on Linkedin Email July 14th, 2026 link
    supporting image

    The South Town Hall parking lot closure is in full effect.

    Some important reminders:

    • Town Hall is accessible via the north entrance on the third floor.
    • The Seniors Centre is accessible via the main entrance via the pedestrian walkway off of John West Way.
    • There is no access across the parking lot from Town Hall to the Seniors Centre. The only access between buildings is via the sidewalk on John West Way.

    The South Town Hall parking lot closure is in full effect.

    Some important reminders:

    • Town Hall is accessible via the north entrance on the third floor.
    • The Seniors Centre is accessible via the main entrance via the pedestrian walkway off of John West Way.
    • There is no access across the parking lot from Town Hall to the Seniors Centre. The only access between buildings is via the sidewalk on John West Way.
  • South Parking Lot Closure - Begins July 14

    Share South Parking Lot Closure - Begins July 14 on Facebook Share South Parking Lot Closure - Begins July 14 on X (formerly Twitter) Share South Parking Lot Closure - Begins July 14 on Linkedin Email South Parking Lot Closure - Begins July 14 link

    Starting Tuesday, July 14, the south parking lot at Aurora Town Hall will be closed to allow our contractor to complete rehabilitation work.

    During this time, visitors are encouraged to use the north parking lot or the permitted on-street parking areas shown in green on the map below.

    Alternative Parking Areas

    Access to the Aurora Seniors' Centre building will remain available throughout construction. Six accessible parking spaces, permitted on-street parking, and a shared bus stop/drop-off zone will be available at this time

    Please note that parking is not permitted within the designated drop-off zone. Refer to the map below for access details.

    Aurora Seniors' Centre Access

    Visitors to Access Aurora should enter Town Hall through the north parking lot and follow the posted signage from the 3rd floor entrance to the 1st floor.

    We appreciate your patience and understanding as these improvements are completed.

    Starting Tuesday, July 14, the south parking lot at Aurora Town Hall will be closed to allow our contractor to complete rehabilitation work.

    During this time, visitors are encouraged to use the north parking lot or the permitted on-street parking areas shown in green on the map below.

    Alternative Parking Areas

    Access to the Aurora Seniors' Centre building will remain available throughout construction. Six accessible parking spaces, permitted on-street parking, and a shared bus stop/drop-off zone will be available at this time

    Please note that parking is not permitted within the designated drop-off zone. Refer to the map below for access details.

    Aurora Seniors' Centre Access

    Visitors to Access Aurora should enter Town Hall through the north parking lot and follow the posted signage from the 3rd floor entrance to the 1st floor.

    We appreciate your patience and understanding as these improvements are completed.

  • July 10th, 2026

    Share July 10th, 2026 on Facebook Share July 10th, 2026 on X (formerly Twitter) Share July 10th, 2026 on Linkedin Email July 10th, 2026 link

    Seniors Centre Walkway:

    The new concrete was placed today! The contractor is on course to have the walkway reopened next week.


    Reflection Space:

    The retaining wall has been successfully reinstated. Crews now continue work on removing and disposing old interlock and concrete.


    Seniors Centre Walkway:

    The new concrete was placed today! The contractor is on course to have the walkway reopened next week.


    Reflection Space:

    The retaining wall has been successfully reinstated. Crews now continue work on removing and disposing old interlock and concrete.


  • July 9th, 2026

    Share July 9th, 2026 on Facebook Share July 9th, 2026 on X (formerly Twitter) Share July 9th, 2026 on Linkedin Email July 9th, 2026 link

    Seniors Centre Walkway:

    Crews are placing concrete formwork. Our concrete pour will be delayed until tomorrow due to today’s threat of thunder showers.


    Reflection Space:

    Work continues on rebuilding the retaining wall.

    Seniors Centre Walkway:

    Crews are placing concrete formwork. Our concrete pour will be delayed until tomorrow due to today’s threat of thunder showers.


    Reflection Space:

    Work continues on rebuilding the retaining wall.

  • July 8th, 2026

    Share July 8th, 2026 on Facebook Share July 8th, 2026 on X (formerly Twitter) Share July 8th, 2026 on Linkedin Email July 8th, 2026 link

    Seniors Centre Walkway:

    Crews are on site fine grading the area before concrete is placed to ensure proper drainage.


    Reflection Space:

    Crews have salvaged an old retaining wall and are now rebuilding it to a higher standard.

    Seniors Centre Walkway:

    Crews are on site fine grading the area before concrete is placed to ensure proper drainage.


    Reflection Space:

    Crews have salvaged an old retaining wall and are now rebuilding it to a higher standard.

  • July 7th, 2026

    Share July 7th, 2026 on Facebook Share July 7th, 2026 on X (formerly Twitter) Share July 7th, 2026 on Linkedin Email July 7th, 2026 link

    Work is underway!

    Crews have begun removals on the Seniors Centre walkway.

    Additionally, the landscaper will begin work on the community reflection space beginning with the required tree removals.

    Work is underway!

    Crews have begun removals on the Seniors Centre walkway.

    Additionally, the landscaper will begin work on the community reflection space beginning with the required tree removals.

  • July 6th, 2026 - Mobilization

    Share July 6th, 2026 - Mobilization on Facebook Share July 6th, 2026 - Mobilization on X (formerly Twitter) Share July 6th, 2026 - Mobilization on Linkedin Email July 6th, 2026 - Mobilization link

    Expect equipment and materials to arrive in the south parking lot this afternoon.
    The contractor will barrel off additional parking spaces tonight for additional storage room.
    Work will begin on the Senior's Centre walkway as of tomorrow.

    Expect equipment and materials to arrive in the south parking lot this afternoon.
    The contractor will barrel off additional parking spaces tonight for additional storage room.
    Work will begin on the Senior's Centre walkway as of tomorrow.

  • July 3rd, 2026 - Contractor Mobilization

    Share July 3rd, 2026 - Contractor Mobilization on Facebook Share July 3rd, 2026 - Contractor Mobilization on X (formerly Twitter) Share July 3rd, 2026 - Contractor Mobilization on Linkedin Email July 3rd, 2026 - Contractor Mobilization link

    Starting July 6th, 2026, Melrose Paving Co will begin their construction mobilization by bringing in materials and equipment into the south parking lot. This will include the removal and replacement of the Senior Center's walkway. The parking lot will remain open until this walkway is completed. The full parking lot closure is expected starting in the week of July 13th, 2026.

    Starting July 6th, 2026, Melrose Paving Co will begin their construction mobilization by bringing in materials and equipment into the south parking lot. This will include the removal and replacement of the Senior Center's walkway. The parking lot will remain open until this walkway is completed. The full parking lot closure is expected starting in the week of July 13th, 2026.

  • Construction Starting Soon

    Share Construction Starting Soon on Facebook Share Construction Starting Soon on X (formerly Twitter) Share Construction Starting Soon on Linkedin Email Construction Starting Soon link
    supporting image

    Beginning the week of July 6th, 2026, Melrose Paving Co. Ltd., will mobilize to Town Hall and begin work on the Senior Centre walkway. This work is being completed in preparation of the full parking lot closure.

    The parking lot will remain open for use until this work is completed. Further updates to follow soon.

    Beginning the week of July 6th, 2026, Melrose Paving Co. Ltd., will mobilize to Town Hall and begin work on the Senior Centre walkway. This work is being completed in preparation of the full parking lot closure.

    The parking lot will remain open for use until this work is completed. Further updates to follow soon.