August 6th, 2026

Parking Lot:

Electrical work is progressing well with crews continuing to install the new wiring throughout the parking lot next week. The crew is expected to begin excavating and preparing the foundations for the new light poles.


Reflection Space:

Work continues to progress in the reflection space. Crews are preparing several new concrete futures with concrete pouring scheduled for tomorrow.

In the image attached, we can see the successful installation of three new soil cells (black squares) to support the root growth of new trees to be planted here.