August 18th, 2026
Parking Lot:
Crews are finalizing concrete work this week and grading the parking lot and preparation for asphalt. Paving is expected to follow shortly.
Reflection Space:
Crews have nearly finished forming the concrete curbs with concrete expected to be poured this week. Once complete, work will move into installing the new interlocking areas.