Gilbank Drive: Sidewalk removals and replacements, along with asphalt removal and road grading, are ongoing. Short duration impacts to driveway access may occur during removals in front of driveways.

McLeod Drive & Lacey Court: Final watermain connections are ongoing, with homes being transitioned back to the permanent watermain this week. Removal of the temporary watermain will also begin.

Marksbury Court: Sidewalk removal and replacement is scheduled to begin this week. Guard rail removal and replacement has been postponed to a later date. Storm sewer lining will begin Monday, September 8. During this work temporary disruptions to vehicle access are expected.

Thank you for your cooperation throughout this project.