McLeod Area Roads Project

Share McLeod Area Roads Project on Facebook Share McLeod Area Roads Project on Twitter Share McLeod Area Roads Project on Linkedin Email McLeod Area Roads Project link

We are making improvements to the streets and infrastructure in the McLeod Drive area (McLeod Drive, Gilibank Drive, Lacey Court and Marksbury Court).

The proposed work will include:

  • Full depth road reconstruction on McLeod Drive and portion of Lacey Court;
  • Full asphalt and curb replacement on Gilbank Drive and portion of Lacey Court;
  • Asphalt mill and overlay on Marksbury Court, with concrete curb spot repairs
  • Watermain lining on McLeod Drive and Lacey Court
  • Storm sewer lining and new guiderail on Marksbury Court
  • Sewer and sidewalk spot repairs and minor road drainage improvements
  • Brightening of existing streetlights with potential addition of a streetlight pole on Marksbury Court

What to expect during construction:

  • Signage will be posted in the area and construction notices will be distributed.
  • Regular construction hours from 7am to 8 pm, Monday to Friday. Contractor may work Saturday as needed.
  • Sidewalks will be closed where needed for repairs.
  • Access to McLeod Dr, Gilbank Dr, Marksbury Ct and Lacey Ct will be for local traffic only during construction. Please be aware of construction activity and personnel.

We are making improvements to the streets and infrastructure in the McLeod Drive area (McLeod Drive, Gilibank Drive, Lacey Court and Marksbury Court).

The proposed work will include:

  • Full depth road reconstruction on McLeod Drive and portion of Lacey Court;
  • Full asphalt and curb replacement on Gilbank Drive and portion of Lacey Court;
  • Asphalt mill and overlay on Marksbury Court, with concrete curb spot repairs
  • Watermain lining on McLeod Drive and Lacey Court
  • Storm sewer lining and new guiderail on Marksbury Court
  • Sewer and sidewalk spot repairs and minor road drainage improvements
  • Brightening of existing streetlights with potential addition of a streetlight pole on Marksbury Court

What to expect during construction:

  • Signage will be posted in the area and construction notices will be distributed.
  • Regular construction hours from 7am to 8 pm, Monday to Friday. Contractor may work Saturday as needed.
  • Sidewalks will be closed where needed for repairs.
  • Access to McLeod Dr, Gilbank Dr, Marksbury Ct and Lacey Ct will be for local traffic only during construction. Please be aware of construction activity and personnel.
  • Project Update - July 4th

    04 Jul 2025
    Share Project Update - July 4th on Facebook Share Project Update - July 4th on Twitter Share Project Update - July 4th on Linkedin Email Project Update - July 4th link

    Temporary watermain installation will continue next week, followed by excavation for sewer lining pits. We'll provide additional updates as the work progresses.

    Thank you.

  • Project Update - June 18th

    18 Jun 2025
    Share Project Update - June 18th on Facebook Share Project Update - June 18th on Twitter Share Project Update - June 18th on Linkedin Email Project Update - June 18th link

    Tree removals have now been completed. Temporary watermain installation is ongoing this week and will continue in the coming days.

    Further updates will be provided as work progresses.

  • Construction Has Begun!

    11 Jun 2025
    Share Construction Has Begun! on Facebook Share Construction Has Begun! on Twitter Share Construction Has Begun! on Linkedin Email Construction Has Begun! link

    Crews have started installing a temporary watermain on Lacy Court and McLeod Drive. Tree removals have are also underway throughout the project area.

    These early works are expected to continue over the next week or two. Thank you for your patience and cooperation as construction progresses.

  • Contractor Mobilization

    03 Jun 2025
    Share Contractor Mobilization on Facebook Share Contractor Mobilization on Twitter Share Contractor Mobilization on Linkedin Email Contractor Mobilization link

    The Contractor Trisan Construction has notified that they will begin mobilizing to the site this week. Residents may notice the delivery of construction materials and equipment as preparations for the upcoming work get underway.

    Thank you.

  • Construction is Starting Soon!

    16 May 2025
    Share Construction is Starting Soon! on Facebook Share Construction is Starting Soon! on Twitter Share Construction is Starting Soon! on Linkedin Email Construction is Starting Soon! link
    supporting image

    Trisan Construction has been contracted by the Town to undertake the rehabilitation of various watermain and road assets on McLeod Drive, Marksbury Court, Gilbank Drive and Lacey Court. It is anticipated the work will commence the week of May 26/June 2 and is expected to be completed by late October.

    Read the full notice now.

  • Join us for a public open house!

    03 Oct 2024
    Share Join us for a public open house! on Facebook Share Join us for a public open house! on Twitter Share Join us for a public open house! on Linkedin Email Join us for a public open house! link
    supporting image


    This is your chance to dive into the details of the planned road and infrastructure improvement for McLeod Drive, Marksbury Court, Gilbank Drive, and Lacey Court.


    Drop in, ask questions, share your thoughts.

Page last updated: 04 Jul 2025, 07:24 AM