Project Update - September 22nd

Gilbank Drive: Paving was completed on Friday. Driveway restorations are scheduled to begin this week (weather permitting).

McLeod Drive & Lacey Court: Road excavation continues on McLeod, and curb removal is underway on Lacey. Short-term driveway access interruptions may occur during excavation; however, access will be restored by the end of each working day.

Marksbury Court: Guard rail replacement has begun, and paving was completed on Friday. Sanitary sewer lining is ongoing, with driveway restorations scheduled to begin this week.