Project Update - September 18th
Gilbank Drive: Road fine grading is now complete. Paving is scheduled for September 19th, with driveway restorations to follow next week.
McLeod Drive & Lacey Court: Road excavation is underway on McLeod. Curb removal on Lacey is expected to begin on September 19 or September 22. Temporary driveway access interruptions may occur during excavation; however, access will be restored by the end of each working day.
Marksbury Court: Guard rail replacement remains postponed. Paving is scheduled for September 19, and sanitary sewer lining activities are ongoing.