Gilbank Drive: Sidewalk removals and replacements are now complete. Asphalt removal and road grading have also been completed. Fine grading and placement of the first layer of asphalt are scheduled in the coming weeks.

McLeod Drive & Lacey Court: Final watermain connections are complete, and all homes have been transitioned back to the permanent watermain. The temporary watermain has been fully removed. Asphalt removal is complete, and road excavation is scheduled to begin today (September 15). Please expect delays during this work. Some driveways may be temporarily inaccessible at times throughout the day as excavation progresses.

Marksbury Court: Sidewalk removal and replacement are complete. Guard rail replacement remains postponed. Asphalt removal and storm sewer lining are both now complete.

Thank you.

Share Project Update - September 15th on Facebook Share Project Update - September 15th on Twitter Share Project Update - September 15th on Linkedin Email Project Update - September 15th link
#<Object:0x00007f6fc852eab0>