George Street Watermain Rehabilitation and Site Servicing

Share George Street Watermain Rehabilitation and Site Servicing on Facebook Share George Street Watermain Rehabilitation and Site Servicing on X (formerly Twitter) Share George Street Watermain Rehabilitation and Site Servicing on Linkedin Email George Street Watermain Rehabilitation and Site Servicing link

Consultation has concluded

Welcome! Thank you for visiting the George Street Servicing and Road Improvements project page. Here you’ll find information about the project, construction updates, and what to expect as work progresses.



What are we doing?

The Town of Aurora is undertaking infrastructure improvements on George Street.
• Installing new water and sanitary service connections.
• Improving stormwater drainage.
• Replacing and realigning the sidewalk and curb on the east side of George Street.
• The road will be rehabilitated during the final stage of construction.

Construction is expected to take place from September to December 2026.

What to expect during construction:

  • Increased construction traffic
  • Lane reduction during working hours
  • Increased noise during working hours
  • Increased dust generation (dust control measures are enforced)
  • Construction fencing to protect the public from open excavations

Welcome! Thank you for visiting the George Street Servicing and Road Improvements project page. Here you’ll find information about the project, construction updates, and what to expect as work progresses.



What are we doing?

The Town of Aurora is undertaking infrastructure improvements on George Street.
• Installing new water and sanitary service connections.
• Improving stormwater drainage.
• Replacing and realigning the sidewalk and curb on the east side of George Street.
• The road will be rehabilitated during the final stage of construction.

Construction is expected to take place from September to December 2026.

What to expect during construction:

  • Increased construction traffic
  • Lane reduction during working hours
  • Increased noise during working hours
  • Increased dust generation (dust control measures are enforced)
  • Construction fencing to protect the public from open excavations
Consultation has concluded
  • Thank You!

    Share Thank You! on Facebook Share Thank You! on X (formerly Twitter) Share Thank You! on Linkedin Email Thank You! link

    Dear Residents,

    We are pleased to inform you that the construction on George Street has now been successfully completed.

    We would like to extend our sincere thanks for your patience, understanding, and cooperation throughout the construction period. We recognize that this work may have caused temporary inconvenience, and we truly appreciate your support as we worked to improve the infrastructure in our community.

    Thank you once again for your cooperation!

    Dear Residents,

    We are pleased to inform you that the construction on George Street has now been successfully completed.

    We would like to extend our sincere thanks for your patience, understanding, and cooperation throughout the construction period. We recognize that this work may have caused temporary inconvenience, and we truly appreciate your support as we worked to improve the infrastructure in our community.

    Thank you once again for your cooperation!

    Consultation has concluded
  • Project Update - November 06, 2026

    Share Project Update - November 06, 2026 on Facebook Share Project Update - November 06, 2026 on X (formerly Twitter) Share Project Update - November 06, 2026 on Linkedin Email Project Update - November 06, 2026 link

    Hello everyone,

    The contractor is scheduled to complete asphalt milling on George Street on Tuesday (Nov 10) and paving on Wednesday (Nov 11), subject to weather conditions.

    Further updates will be provided as the work progresses.

    Thank you for your patience and cooperation.


    Hello everyone,

    The contractor is scheduled to complete asphalt milling on George Street on Tuesday (Nov 10) and paving on Wednesday (Nov 11), subject to weather conditions.

    Further updates will be provided as the work progresses.

    Thank you for your patience and cooperation.


    Consultation has concluded
  • Project Update - October 31, 2026

    Share Project Update - October 31, 2026 on Facebook Share Project Update - October 31, 2026 on X (formerly Twitter) Share Project Update - October 31, 2026 on Linkedin Email Project Update - October 31, 2026 link

    Hello everyone,

    We have completed the concrete curb and sidewalk work this week. The restoration of the utility trenches has also been completed.

    Please note that the contractor will be onsite this Saturday, October 31, to complete minor works, including topsoil placement and sod installation.

    Wishing everyone a safe and happy Halloween! 🎃

    Hello everyone,

    We have completed the concrete curb and sidewalk work this week. The restoration of the utility trenches has also been completed.

    Please note that the contractor will be onsite this Saturday, October 31, to complete minor works, including topsoil placement and sod installation.

    Wishing everyone a safe and happy Halloween! 🎃

    Consultation has concluded
  • Project Update - October 26 to 30, 2026

    Share Project Update - October 26 to 30, 2026 on Facebook Share Project Update - October 26 to 30, 2026 on X (formerly Twitter) Share Project Update - October 26 to 30, 2026 on Linkedin Email Project Update - October 26 to 30, 2026 link

    Hello,

    The underground utility work on George Street was successfully completed last week. This week, the contractor will proceed with the road restoration works, including curb and sidewalk removal and reinstallation.

    Further updates will be provided as the work progresses.

    Thank you for your patience and cooperation.

    Hello,

    The underground utility work on George Street was successfully completed last week. This week, the contractor will proceed with the road restoration works, including curb and sidewalk removal and reinstallation.

    Further updates will be provided as the work progresses.

    Thank you for your patience and cooperation.

    Consultation has concluded
  • Project Update - October 16, 2026

    Share Project Update - October 16, 2026 on Facebook Share Project Update - October 16, 2026 on X (formerly Twitter) Share Project Update - October 16, 2026 on Linkedin Email Project Update - October 16, 2026 link

    Hello everyone,

    The contractor successfully completed the watermain commissioning on George Street today.

    Have a nice weekend!

    Thank you for your cooperation.

    Hello everyone,

    The contractor successfully completed the watermain commissioning on George Street today.

    Have a nice weekend!

    Thank you for your cooperation.

    Consultation has concluded
  • Project Update - October 19 to 23, 2026

    Share Project Update - October 19 to 23, 2026 on Facebook Share Project Update - October 19 to 23, 2026 on X (formerly Twitter) Share Project Update - October 19 to 23, 2026 on Linkedin Email Project Update - October 19 to 23, 2026 link

    Hello everyone,

    The contractor will be installing the sanitary and water service connections on George Street this week. Please drive carefully when travelling through the active construction area.

    Further updates will be provided as the work progresses.

    Thank you for your patience and cooperation.

    Hello everyone,

    The contractor will be installing the sanitary and water service connections on George Street this week. Please drive carefully when travelling through the active construction area.

    Further updates will be provided as the work progresses.

    Thank you for your patience and cooperation.

    Consultation has concluded
  • Project Update - Water shutdown

    Share Project Update - Water shutdown on Facebook Share Project Update - Water shutdown on X (formerly Twitter) Share Project Update - Water shutdown on Linkedin Email Project Update - Water shutdown link

    Hello,

    Please be advised that water service to 116 and 123 George Street will be temporarily disrupted on Friday, October 16, 2026, from 8:00 a.m. to 4:30 p.m. due to the commissioning of a newly installed watermain on George Street.

    The water service disruption times provided are estimates and may change due to weather conditions or other unforeseen circumstances. We will make every effort to restore service as quickly as possible.

    We apologize for any inconvenience this may cause and appreciate your cooperation while we work to improve the infrastructure in your area.

    Thanks!

    Hello,

    Please be advised that water service to 116 and 123 George Street will be temporarily disrupted on Friday, October 16, 2026, from 8:00 a.m. to 4:30 p.m. due to the commissioning of a newly installed watermain on George Street.

    The water service disruption times provided are estimates and may change due to weather conditions or other unforeseen circumstances. We will make every effort to restore service as quickly as possible.

    We apologize for any inconvenience this may cause and appreciate your cooperation while we work to improve the infrastructure in your area.

    Thanks!

    Consultation has concluded
  • Project Update - October 13 to 16, 2026

    Share Project Update - October 13 to 16, 2026 on Facebook Share Project Update - October 13 to 16, 2026 on X (formerly Twitter) Share Project Update - October 13 to 16, 2026 on Linkedin Email Project Update - October 13 to 16, 2026 link

    Hello everyone,

    The contractor will continue the sanitary main installation this week.

    Further updates will be provided as work progresses.

    Thank you for your cooperation.

    Hello everyone,

    The contractor will continue the sanitary main installation this week.

    Further updates will be provided as work progresses.

    Thank you for your cooperation.

    Consultation has concluded
  • Project Update- October 5 to 9, 2026

    Share Project Update- October 5 to 9, 2026 on Facebook Share Project Update- October 5 to 9, 2026 on X (formerly Twitter) Share Project Update- October 5 to 9, 2026 on Linkedin Email Project Update- October 5 to 9, 2026 link

    Hello everyone,

    The contractor will install the watermain on Monday and begin the watermain testing procedure on Tuesday. They will also begin installing the sanitary main on George Street on Tuesday and continue the work until Friday.

    Further updates will be provided as work progresses.

    Thank you for your patience.

    Hello everyone,

    The contractor will install the watermain on Monday and begin the watermain testing procedure on Tuesday. They will also begin installing the sanitary main on George Street on Tuesday and continue the work until Friday.

    Further updates will be provided as work progresses.

    Thank you for your patience.

    Consultation has concluded
  • Project Update - October 3, 2026

    Share Project Update - October 3, 2026 on Facebook Share Project Update - October 3, 2026 on X (formerly Twitter) Share Project Update - October 3, 2026 on Linkedin Email Project Update - October 3, 2026 link

    Hello,

    Please be advised that the contractor will be onsite for a few hours on Saturday (Oct 3rd), to complete the temporary asphalt patch work.

    Further updates will be provided as work progresses.

    Have a nice weekend!

    Thank you

    Hello,

    Please be advised that the contractor will be onsite for a few hours on Saturday (Oct 3rd), to complete the temporary asphalt patch work.

    Further updates will be provided as work progresses.

    Have a nice weekend!

    Thank you

    Consultation has concluded