Project Update - September 29 to October 2, 2026

Hello,

The contractor’s surveyor will be onsite Wednesday for the layout. Asphalt saw cutting is scheduled for Thursday, and road excavation for the watermain installation will begin on Friday.

Further updates will be provided as work progresses.