George Street Watermain Rehabilitation and Site Servicing

Share George Street Watermain Rehabilitation and Site Servicing on Facebook Share George Street Watermain Rehabilitation and Site Servicing on X (formerly Twitter) Share George Street Watermain Rehabilitation and Site Servicing on Linkedin Email George Street Watermain Rehabilitation and Site Servicing link

Welcome! Thank you for visiting the George Street Servicing and Road Improvements project page. Here you’ll find information about the project, construction updates, and what to expect as work progresses.



What are we doing?

The Town of Aurora is undertaking infrastructure improvements on George Street.
• Installing new water and sanitary service connections.
• Improving stormwater drainage.
• Replacing and realigning the sidewalk and curb on the east side of George Street.
• The road will be rehabilitated during the final stage of construction.

Construction is expected to take place from September to December 2026.

What to expect during construction:

  • Increased construction traffic
  • Lane reduction during working hours
  • Increased noise during working hours
  • Increased dust generation (dust control measures are enforced)
  • Construction fencing to protect the public from open excavations

Welcome! Thank you for visiting the George Street Servicing and Road Improvements project page. Here you’ll find information about the project, construction updates, and what to expect as work progresses.



What are we doing?

The Town of Aurora is undertaking infrastructure improvements on George Street.
• Installing new water and sanitary service connections.
• Improving stormwater drainage.
• Replacing and realigning the sidewalk and curb on the east side of George Street.
• The road will be rehabilitated during the final stage of construction.

Construction is expected to take place from September to December 2026.

What to expect during construction:

  • Increased construction traffic
  • Lane reduction during working hours
  • Increased noise during working hours
  • Increased dust generation (dust control measures are enforced)
  • Construction fencing to protect the public from open excavations
  • Project Update - October 26 to 30, 2026

    Share Project Update - October 26 to 30, 2026 on Facebook Share Project Update - October 26 to 30, 2026 on X (formerly Twitter) Share Project Update - October 26 to 30, 2026 on Linkedin Email Project Update - October 26 to 30, 2026 link

    Hello,

    The underground utility work on George Street was successfully completed last week. This week, the contractor will proceed with the road restoration works, including curb and sidewalk removal and reinstallation.

    Further updates will be provided as the work progresses.

    Thank you for your patience and cooperation.

    Hello,

    The underground utility work on George Street was successfully completed last week. This week, the contractor will proceed with the road restoration works, including curb and sidewalk removal and reinstallation.

    Further updates will be provided as the work progresses.

    Thank you for your patience and cooperation.

  • Project Update - October 19 to 23, 2026

    Share Project Update - October 19 to 23, 2026 on Facebook Share Project Update - October 19 to 23, 2026 on X (formerly Twitter) Share Project Update - October 19 to 23, 2026 on Linkedin Email Project Update - October 19 to 23, 2026 link

    Hello everyone,

    The contractor will be installing the sanitary and water service connections on George Street this week. Please drive carefully when travelling through the active construction area.

    Further updates will be provided as the work progresses.

    Thank you for your patience and cooperation.

    Hello everyone,

    The contractor will be installing the sanitary and water service connections on George Street this week. Please drive carefully when travelling through the active construction area.

    Further updates will be provided as the work progresses.

    Thank you for your patience and cooperation.

  • Project Update - October 16, 2026

    Share Project Update - October 16, 2026 on Facebook Share Project Update - October 16, 2026 on X (formerly Twitter) Share Project Update - October 16, 2026 on Linkedin Email Project Update - October 16, 2026 link

    Hello everyone,

    The contractor successfully completed the watermain commissioning on George Street today.

    Have a nice weekend!

    Thank you for your cooperation.

    Hello everyone,

    The contractor successfully completed the watermain commissioning on George Street today.

    Have a nice weekend!

    Thank you for your cooperation.

  • Project Update - Water shutdown

    Share Project Update - Water shutdown on Facebook Share Project Update - Water shutdown on X (formerly Twitter) Share Project Update - Water shutdown on Linkedin Email Project Update - Water shutdown link

    Hello,

    Please be advised that water service to 116 and 123 George Street will be temporarily disrupted on Friday, October 16, 2026, from 8:00 a.m. to 4:30 p.m. due to the commissioning of a newly installed watermain on George Street.

    The water service disruption times provided are estimates and may change due to weather conditions or other unforeseen circumstances. We will make every effort to restore service as quickly as possible.

    We apologize for any inconvenience this may cause and appreciate your cooperation while we work to improve the infrastructure in your area.

    Thanks!

    Hello,

    Please be advised that water service to 116 and 123 George Street will be temporarily disrupted on Friday, October 16, 2026, from 8:00 a.m. to 4:30 p.m. due to the commissioning of a newly installed watermain on George Street.

    The water service disruption times provided are estimates and may change due to weather conditions or other unforeseen circumstances. We will make every effort to restore service as quickly as possible.

    We apologize for any inconvenience this may cause and appreciate your cooperation while we work to improve the infrastructure in your area.

    Thanks!

  • Project Update - October 13 to 16, 2026

    Share Project Update - October 13 to 16, 2026 on Facebook Share Project Update - October 13 to 16, 2026 on X (formerly Twitter) Share Project Update - October 13 to 16, 2026 on Linkedin Email Project Update - October 13 to 16, 2026 link

    Hello everyone,

    The contractor will continue the sanitary main installation this week.

    Further updates will be provided as work progresses.

    Thank you for your cooperation.

    Hello everyone,

    The contractor will continue the sanitary main installation this week.

    Further updates will be provided as work progresses.

    Thank you for your cooperation.

  • Project Update- October 5 to 9, 2026

    Share Project Update- October 5 to 9, 2026 on Facebook Share Project Update- October 5 to 9, 2026 on X (formerly Twitter) Share Project Update- October 5 to 9, 2026 on Linkedin Email Project Update- October 5 to 9, 2026 link

    Hello everyone,

    The contractor will install the watermain on Monday and begin the watermain testing procedure on Tuesday. They will also begin installing the sanitary main on George Street on Tuesday and continue the work until Friday.

    Further updates will be provided as work progresses.

    Thank you for your patience.

    Hello everyone,

    The contractor will install the watermain on Monday and begin the watermain testing procedure on Tuesday. They will also begin installing the sanitary main on George Street on Tuesday and continue the work until Friday.

    Further updates will be provided as work progresses.

    Thank you for your patience.

  • Project Update - October 3, 2026

    Share Project Update - October 3, 2026 on Facebook Share Project Update - October 3, 2026 on X (formerly Twitter) Share Project Update - October 3, 2026 on Linkedin Email Project Update - October 3, 2026 link

    Hello,

    Please be advised that the contractor will be onsite for a few hours on Saturday (Oct 3rd), to complete the temporary asphalt patch work.

    Further updates will be provided as work progresses.

    Have a nice weekend!

    Thank you

    Hello,

    Please be advised that the contractor will be onsite for a few hours on Saturday (Oct 3rd), to complete the temporary asphalt patch work.

    Further updates will be provided as work progresses.

    Have a nice weekend!

    Thank you

  • Project Update - September 29 to October 2, 2026

    Share Project Update - September 29 to October 2, 2026 on Facebook Share Project Update - September 29 to October 2, 2026 on X (formerly Twitter) Share Project Update - September 29 to October 2, 2026 on Linkedin Email Project Update - September 29 to October 2, 2026 link

    Hello,

    The contractor’s surveyor will be onsite Wednesday for the layout. Asphalt saw cutting is scheduled for Thursday, and road excavation for the watermain installation will begin on Friday.

    Further updates will be provided as work progresses.

    Thank you

    Hello,

    The contractor’s surveyor will be onsite Wednesday for the layout. Asphalt saw cutting is scheduled for Thursday, and road excavation for the watermain installation will begin on Friday.

    Further updates will be provided as work progresses.

    Thank you

  • Project Update - September 28, 2026

    Share Project Update - September 28, 2026 on Facebook Share Project Update - September 28, 2026 on X (formerly Twitter) Share Project Update - September 28, 2026 on Linkedin Email Project Update - September 28, 2026 link

    Hello all,

    Select trees were removed this morning. All six (6) of the trees were chipped and removed from the site.

    Additional materials are scheduled to be delivered within the next two days. Road saw cuts are to begin on Wednesday to aid in the removal of asphalt coming next week.

    Stay tuned for further updates.

    Thank you.

    Hello all,

    Select trees were removed this morning. All six (6) of the trees were chipped and removed from the site.

    Additional materials are scheduled to be delivered within the next two days. Road saw cuts are to begin on Wednesday to aid in the removal of asphalt coming next week.

    Stay tuned for further updates.

    Thank you.

  • Project Update - September 21, 2026

    Share Project Update - September 21, 2026 on Facebook Share Project Update - September 21, 2026 on X (formerly Twitter) Share Project Update - September 21, 2026 on Linkedin Email Project Update - September 21, 2026 link

    Hello,

    The contractor is scheduled to commence work during the week of September 28, including mobilization, tree removals, and material deliveries. The surveyor will be onsite on September 24 for the layout work.

    Further updates will be provided as work progresses.

    Thank you

    Hello,

    The contractor is scheduled to commence work during the week of September 28, including mobilization, tree removals, and material deliveries. The surveyor will be onsite on September 24 for the layout work.

    Further updates will be provided as work progresses.

    Thank you

Page last updated: 23 Oct 2026, 01:31 PM