Share Project Update - December 04, 2025 on Facebook
Share Project Update - December 04, 2025 on Linkedin
Email Project Update - December 04, 2025 link
Hello,
Storm and sanitary underground works are expected to be completed by this week. The temporary asphalt paving of trenches and site clean‑up is scheduled for early next week, weather permitting.
Thank you for your patience.
Share Project Update - November 21, 2025 on Facebook
Share Project Update - November 21, 2025 on Linkedin
Email Project Update - November 21, 2025 link
Hello,
The sanitary main installation with service connection is completed for this project. The crew will continue with drainage work from next week.
Further updates will be provided as work progresses.
Thank you for your patience.
Share Project Update - November 14, 2025 on Facebook
Share Project Update - November 14, 2025 on Linkedin
Email Project Update - November 14, 2025 link
Hello everyone,
We started installing the sanitary main this week and expect to complete it by early next week. Once finished, we will resume work on the drainage main installation.
Further updates will be provided as work progresses.
Thank you for your patience.
Share Project Update - November 06, 2025 on Facebook
Share Project Update - November 06, 2025 on Linkedin
Email Project Update - November 06, 2025 link
Hello everyone,
The drainage main installation is ongoing this week and will continue in the coming days.
Furter updates will be provided as work progresses.
Thank you for your patience.
Share Halloween Safety Reminder on Facebook
Share Halloween Safety Reminder on Linkedin
Email Halloween Safety Reminder link
As construction work continues in this area, we remind residents and visitors to remain cautious while out on Halloween night. Please drive carefully, especially over loose gravel and trench patches.
Wishing everyone a safe and happy Halloween! 🎃
Share Construction Has Begun! on Facebook
Share Construction Has Begun! on Linkedin
Email Construction Has Begun! link
The crew has begun asphalt saw-cutting, excavation, and daylighting of existing underground utilities using a Hydrovac. They will continue with trench excavation for the drainage main installation on November 3rd.
Share Contractor Mobilization on Facebook
Share Contractor Mobilization on Linkedin
Email Contractor Mobilization link
The contractor Pacific Paving has notified that they will begin mobilizing to the site next week. Residents may notice the delivery of construction materials and equipment as preparations for the upcoming work get underway.
Thank you.
Share Construction is starting soon! on Facebook
Share Construction is starting soon! on Linkedin
Email Construction is starting soon! link
Pacific Paving has been contracted by the Town to reconstruct Centre Street from Yonge Street to Spruce Street. • Phase 1 is scheduled to begin the week of October 6th and is expected to be completed by December 2025. This phase includes underground utility work.• Phase 2 is scheduled to commence in the spring of 2026 and will include the road rehabilitation work. Read the full notice now.