Watermain Decommissioning at 15390 & 15408 Yonge Street
Share Watermain Decommissioning at 15390 & 15408 Yonge Street on FacebookShare Watermain Decommissioning at 15390 & 15408 Yonge Street on TwitterShare Watermain Decommissioning at 15390 & 15408 Yonge Street on LinkedinEmail Watermain Decommissioning at 15390 & 15408 Yonge Street link
The Town is planning to decommission a section of 350mm asbestos-cement watermain located between 15390 and 15408 Yonge Street. This pipe was installed in 1957 and, during a recent inspection following a watermain break, we found it to be in poor condition. Additionally, part of this watermain runs through private property at 15408 Yonge Street, where the Town does not have an easement, making it difficult to properly maintain.
Because of its age, condition, and location, about 200 metres of this watermain will be taken out of service. Our hydraulic modelling shows that removing this section will have little to no impact on the Town’s overall water distribution system.
As part of the project, the service line that currently supplies the condo building at 15390 Yonge Street will be disconnected from the old watermain and replaced with a new connection directly to the watermain on Yonge Street.
Overall, this work will help remove outdated infrastructure and upgrade water connections, improving water quality and extending the lifespan of the system.
The Town is planning to decommission a section of 350mm asbestos-cement watermain located between 15390 and 15408 Yonge Street. This pipe was installed in 1957 and, during a recent inspection following a watermain break, we found it to be in poor condition. Additionally, part of this watermain runs through private property at 15408 Yonge Street, where the Town does not have an easement, making it difficult to properly maintain.
Because of its age, condition, and location, about 200 metres of this watermain will be taken out of service. Our hydraulic modelling shows that removing this section will have little to no impact on the Town’s overall water distribution system.
As part of the project, the service line that currently supplies the condo building at 15390 Yonge Street will be disconnected from the old watermain and replaced with a new connection directly to the watermain on Yonge Street.
Overall, this work will help remove outdated infrastructure and upgrade water connections, improving water quality and extending the lifespan of the system.
Share Thank You! on FacebookShare Thank You! on TwitterShare Thank You! on LinkedinEmail Thank You! link
Dear Residents,
We are pleased to inform you that the watermain project on Yonge Street has now been successfully completed.
We would like to extend our sincere thanks for your patience, understanding, and cooperation throughout the construction period. We recognize that this work may have caused temporary inconvenience, and we truly appreciate your support as we worked to improve the infrastructure in our community.
Thank you once again for your cooperation!
Dear Residents,
We are pleased to inform you that the watermain project on Yonge Street has now been successfully completed.
We would like to extend our sincere thanks for your patience, understanding, and cooperation throughout the construction period. We recognize that this work may have caused temporary inconvenience, and we truly appreciate your support as we worked to improve the infrastructure in our community.
Share Temporary water shutdown at 15390 Yonge St on FacebookShare Temporary water shutdown at 15390 Yonge St on TwitterShare Temporary water shutdown at 15390 Yonge St on LinkedinEmail Temporary water shutdown at 15390 Yonge St link
Hello,
Please note that on April 30, 2026 (Thursday), you will experience a temporary disruption to water service between the hours of 7:30 a.m. and 5 p.m. The disruption is due to new installed watermain commissioning to the building.
The water disruption times provided are estimates and may change due to unforeseen circumstances. We will do our best to restore service as quickly as possible.
We apologize for any inconvenience this may cause and appreciate your cooperation while we work to improve the infrastructure in your area.
Thank you.
Hello,
Please note that on April 30, 2026 (Thursday), you will experience a temporary disruption to water service between the hours of 7:30 a.m. and 5 p.m. The disruption is due to new installed watermain commissioning to the building.
The water disruption times provided are estimates and may change due to unforeseen circumstances. We will do our best to restore service as quickly as possible.
We apologize for any inconvenience this may cause and appreciate your cooperation while we work to improve the infrastructure in your area.
Share Driveway Access and Parking Impacts at 15390 Yonge St on FacebookShare Driveway Access and Parking Impacts at 15390 Yonge St on TwitterShare Driveway Access and Parking Impacts at 15390 Yonge St on LinkedinEmail Driveway Access and Parking Impacts at 15390 Yonge St link
We would like to thank residents for their patience and cooperation during the first closure work. The contractor is scheduled to implement a second closure from April 30 at 7:00 am to May 01 at 7:00 p.m to complete the watermain commissioning and permanent asphalt restoration work.
• Due to the narrow driveway and limited space required for construction activities, vehicle access to and from the building (15390 Yonge St) will be temporarily closed during the second closure.
• Temporary parking for residents and visitors of the building will be available at the Aurora Community Centre, located at 1 Community Centre Ln, Aurora, ON L4G 7B1 (See attached map).
• Residents are advised to park their vehicles at the Aurora Community Centre during periods when access is closed.
We would like to thank residents for their patience and cooperation during the first closure work. The contractor is scheduled to implement a second closure from April 30 at 7:00 am to May 01 at 7:00 p.m to complete the watermain commissioning and permanent asphalt restoration work.
• Due to the narrow driveway and limited space required for construction activities, vehicle access to and from the building (15390 Yonge St) will be temporarily closed during the second closure.
• Temporary parking for residents and visitors of the building will be available at the Aurora Community Centre, located at 1 Community Centre Ln, Aurora, ON L4G 7B1 (See attached map).
• Residents are advised to park their vehicles at the Aurora Community Centre during periods when access is closed.
Share Construction Has Begun! on FacebookShare Construction Has Begun! on TwitterShare Construction Has Begun! on LinkedinEmail Construction Has Begun! link
The crew has begun construction for this project and will continue with the installation of the water service connection for now.
The crew has begun construction for this project and will continue with the installation of the water service connection for now.
Share Construction is starting soon! on FacebookShare Construction is starting soon! on TwitterShare Construction is starting soon! on LinkedinEmail Construction is starting soon! link
Rabcon Construction has been contracted by the Town to install a new watermain at 15390 Yonge St. It is anticipated the construction work will commence the week of April 13, 2026 and is expected to be completed by May 2026.Read the full notice now.
Rabcon Construction has been contracted by the Town to install a new watermain at 15390 Yonge St. It is anticipated the construction work will commence the week of April 13, 2026 and is expected to be completed by May 2026.Read the full notice now.