Construction Update

Work at Yonge and Wellington continues to progress.

  • The concrete sidewalk and curb replacement work is now complete at the south-east, south-west and north-east corners.
  • Removals and excavation work is now being carried out at the north-west corner for the right turn lane construction. The right turn lane construction is expected to continue for the next 2 to 3 weeks.

Note: During the construction of the right turn lane over these next few weeks, it is anticipated that there will be times when pedestrian access will be restricted at the north-west corner. Pedestrians are advised to navigate around the intersection using the other three corners during those time.

Share Construction Update on Facebook Share Construction Update on Twitter Share Construction Update on Linkedin Email Construction Update link

Consultation has concluded

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>