Winter Update
Hello everyone,
The streetlights have now been replaced. We are going to wait until the spring to come back to site. We will address any deficiencies and we will restore the entire site with new topsoil and sod. We do not have an exact date for paving the last layer of asphalt. It will most likely be later in the year, maybe early fall. Paving the top asphalt will take 1-2 days to prepare the and 1 day to pave.
Thanks
Share Winter Update on Facebook
Share Winter Update on Twitter
Share Winter Update on Linkedin
Email Winter Update link
