When will the project be completed

    Construction should be completed in early December of 2024. We will pave the base course of asphalt and then return in the fall of 2025 to pave the top course of asphalt. We do this because we want to make sure we do not have any issues before we place the final product. 

    Where can I park now that the contractor is occupying the road or blocking my driveway?

    The Town has constructed a temporary parking lot off Henderson for Poplar residents of the York North Condominium Corporation #2  to use. 

    Residents from YCC 207 can park behind the LCBO.

    You can call Steven Ferro 289-221-3299 if you have any issues with a blocked driveway

    What's happening with garbage collection during construction

    The garbage truck cannot make it through Poplar Crescent while the equipment is working on the road. 

    The Town has made arrangements with Trisan Construction to ensure that your garbage collection is not interrupted. 

    Your garbage collection will not be affected. Please bring your garbage out as normal and Trisan will bring it to Henderson Drive for the garbage truck to collect and they will also return the bins. 

    We encourage the use of plastic bags for recycling and garbage (no bins).This will make things a bit easier for the contractor 

    Who can I call if I have questions or concerns

    Steven Ferro is the administrator and inspector for this project. He is on site every day. 

    He can be reached at 289-221-3299