McLeod Area Roads Project
We are making improvements to the streets and infrastructure in the McLeod Drive area (McLeod Drive, Gilibank Drive, Lacey Court and Marksbury Court).
The proposed work will include:
- Full depth road reconstruction on McLeod Drive and portion of Lacey Court;
- Full asphalt and curb replacement on Gilbank Drive and portion of Lacey Court;
- Asphalt mill and overlay on Marksbury Court, with concrete curb spot repairs
- Watermain lining on McLeod Drive and Lacey Court
- Storm sewer lining and new guiderail on Marksbury Court
- Sewer and sidewalk spot repairs and minor road drainage improvements
- Brightening of existing streetlights with potential addition ofContinue reading
We are making improvements to the streets and infrastructure in the McLeod Drive area (McLeod Drive, Gilibank Drive, Lacey Court and Marksbury Court).
The proposed work will include:
- Full depth road reconstruction on McLeod Drive and portion of Lacey Court;
- Full asphalt and curb replacement on Gilbank Drive and portion of Lacey Court;
- Asphalt mill and overlay on Marksbury Court, with concrete curb spot repairs
- Watermain lining on McLeod Drive and Lacey Court
- Storm sewer lining and new guiderail on Marksbury Court
- Sewer and sidewalk spot repairs and minor road drainage improvements
- Brightening of existing streetlights with potential addition of a streetlight pole on Marksbury Court
What to expect during construction:
- Signage will be posted in the area and construction notices will be distributed.
- Regular construction hours from 7am to 8 pm, Monday to Friday. Contractor may work Saturday as needed.
- Sidewalks will be closed where needed for repairs.
- Access to McLeod Dr, Gilbank Dr, Marksbury Ct and Lacey Ct will be for local traffic only during construction. Please be aware of construction activity and personnel.
-
Project Update - September 3rd
Share Project Update - September 3rd on Facebook Share Project Update - September 3rd on Twitter Share Project Update - September 3rd on Linkedin Email Project Update - September 3rd linkHello everyone,
Work is progressing across multiple areas of the McLeod project area:
Gilbank Drive: Sidewalk removals and replacements will begin this week, along with asphalt removal and road grading.
McLeod Drive & Lacey Court: Final watermain connections are scheduled to begin this week, with affected homes being transitioned back to the permanent watermain. Crews will also be completing various underground repairs on McLeod.
Marksbury Court: Sidewalk and guard rail removals and replacements are set to begin this week.
Further updates will be provided as the project continues to advance.
-
Project Update - July 29th
Share Project Update - July 29th on Facebook Share Project Update - July 29th on Twitter Share Project Update - July 29th on Linkedin Email Project Update - July 29th linkWatermain lining will continue throughout this week. Starting on the week of August 4th, crews will begin replacing watermain valves and hydrants.
On Gilbank Drive, curb removal is scheduled to begin on July 31st. Driveway access will remain available throughout the long weekend, however, during the week of August 4th, some driveways may be temporarily inaccessible for approximately 2-3 days while concrete preparation and pouring take place.
-
Project Update - July 23rd
Share Project Update - July 23rd on Facebook Share Project Update - July 23rd on Twitter Share Project Update - July 23rd on Linkedin Email Project Update - July 23rd linkHello everyone,
The temporary watermain is now active and servicing all affected homes. Work is currently underway to line the underground watermain, in addition to the removal and replacement works of various catch basins.
Thank you for your patience.
-
Project Update - July 4th
Share Project Update - July 4th on Facebook Share Project Update - July 4th on Twitter Share Project Update - July 4th on Linkedin Email Project Update - July 4th linkTemporary watermain installation will continue next week, followed by excavation for sewer lining pits. We'll provide additional updates as the work progresses.
Thank you.
-
Project Update - June 18th
Share Project Update - June 18th on Facebook Share Project Update - June 18th on Twitter Share Project Update - June 18th on Linkedin Email Project Update - June 18th linkTree removals have now been completed. Temporary watermain installation is ongoing this week and will continue in the coming days.
Further updates will be provided as work progresses.
-
Construction Has Begun!
Share Construction Has Begun! on Facebook Share Construction Has Begun! on Twitter Share Construction Has Begun! on Linkedin Email Construction Has Begun! linkCrews have started installing a temporary watermain on Lacy Court and McLeod Drive. Tree removals have are also underway throughout the project area.
These early works are expected to continue over the next week or two. Thank you for your patience and cooperation as construction progresses.
-
Contractor Mobilization
Share Contractor Mobilization on Facebook Share Contractor Mobilization on Twitter Share Contractor Mobilization on Linkedin Email Contractor Mobilization linkThe Contractor Trisan Construction has notified that they will begin mobilizing to the site this week. Residents may notice the delivery of construction materials and equipment as preparations for the upcoming work get underway.
Thank you.
-
Construction is Starting Soon!
Share Construction is Starting Soon! on Facebook Share Construction is Starting Soon! on Twitter Share Construction is Starting Soon! on Linkedin Email Construction is Starting Soon! link
Trisan Construction has been contracted by the Town to undertake the rehabilitation of various watermain and road assets on McLeod Drive, Marksbury Court, Gilbank Drive and Lacey Court. It is anticipated the work will commence the week of May 26/June 2 and is expected to be completed by late October.
-
Join us for a public open house!
Share Join us for a public open house! on Facebook Share Join us for a public open house! on Twitter Share Join us for a public open house! on Linkedin Email Join us for a public open house! link
This is your chance to dive into the details of the planned road and infrastructure improvement for McLeod Drive, Marksbury Court, Gilbank Drive, and Lacey Court.
Drop in, ask questions, share your thoughts.
Signup Banner
Who's Listening
-
JC
Email jcarnovale@aurora.ca
Key Dates
-
October 22 2024
Lifecycle
-
Phase 1- Design
McLeod Area Roads Project has finished this stageConceptual Design
-
Phase 2- Finalize Design & Issue for Tender
McLeod Area Roads Project has finished this stageWinter 2024
-
Phase 3- Construction
McLeod Area Roads Project is currently at this stageSpring 2025
-
Phase 4- Anticipated Completion
this is an upcoming stage for McLeod Area Roads ProjectNovember 2025