Timelapse Spring 2023

In this timelapse, watch months of progress in 60 seconds at Aurora Town Square. Throughout Spring 2023, exterior metal siding panels along the north and west elevations of the new Museum & Cultural Centre (NMCC) were installed, precast concrete was placed along the Amphitheatre seats, concrete was poured on the Treasure Hill Bridge and the steel stair was placed, excavation took place under the Bridge where a planter wall was also poured. Interior fit-up of the NMCC continued, including drywall, electrical, and mechanical works. In the basement level, tiling installation commenced, the passenger elevator was installed, and more.